RFI Logging and Tracking SOP

Use this when: Questions to the design team are getting lost, or nobody can say which ones are still open.

Download as a text file

Owner: [project coordinator]

1. Log each RFI before sending it: number, date, drawing or spec reference, question, and who asked.
2. Write one question per RFI. Attach photos or markups.
3. Propose a solution if you have one, and mark any cost or schedule impact.
4. Set a required response date based on the work it affects.
5. Send it through the agreed channel, and copy the people the contract requires.
6. Review open RFIs at the weekly site meeting. Chase any that are overdue.
7. When answered, tell the crew and update the drawings on site.
8. If the answer changes cost or schedule, raise a change notice right away.
9. Close the RFI in the log, and file the response.

Before you use this: Your contract may set notice periods for changes and delays, so check them. A late notice can cost you the claim.

Fill in the items in square brackets and adapt this to your business. It's a starting point, not legal or professional advice.

More for construction

Bid Follow-Up Call Script

You've submitted a bid and want to learn where it stands without sounding pushy.

Call script.

AI Prompt to Pull Requirements from Bid Documents

You need a first-pass checklist from a large tender package, for an estimator to verify.

AI prompt.

More sops

New Listing Launch SOP

A listing agreement is signed and you need every launch to happen the same way.

Real estate. SOP.

Service Call Close-Out SOP for Technicians

Job notes, photos and follow-ups vary from one technician to the next.

HVAC and home services. SOP.

Leak Inspection Report SOP

Reports differ by technician, and managers or insurers keep coming back with questions.

Leak detection and infrastructure. SOP.

Check your key numbers with the Operator ScorecardSAZ's construction practice